Notes, 30 June 2015

  • Steven scheduled meetings in July with hardware suppliers to consider door handles, hinges, etc.
  • Barry Samsel from Custom Plumbing checked the “barrel-style” P-trap for mudroom sink, confirmed it will comply with City of Austin building codes.
  • Steven added the mudroom sink and bathroom vanities to the specification documents.
  • Mark Rehberg advises that Ben Feldt, engineer, did not deliver the structural framing plans he promised for 29 June. Mark is chasing Ben. Update: Plans delivered!
  • Steven spoke with Bryan Mitchell from Carrier. The Cor Internet-connected thermostats continue in development and will be streamed into Emerald Hill as soon as available, probably late 4Q 2015.