Ron is home sick. Day three. He and Steven suspect a virus. The plumber was sick a couple of weeks back. The garage door company pushed back into next week because the install team is down. Steven compared symptoms with Peter, one of the carpenters — sinus cavities so blocked you gasp for air. Combined with allergies to ceder pollen, because ceder is off the scale.
We campaign on without our leader …
Above, the team from Gilsa continues to lay weed block and cover it with gravel, extending the gravel deck off the kitchen side door around to the front of the house.

Steven signed off on change order 26 — we went $600 over on the lighting budget.
Steven also signed off on draw 7 — and Ranserve has begun to reconcile all the line items, change orders, monies not spent, as we approach what promises to be the final month of construction.
It’s one-third the massive truck that Ron drives, but Steven was able to transport two eight-foot-long and two six-foot-long lighting tracks inside his serviceable Honda Element from Lights Fantastic to Emerald Hill. Now the electricians can finish putting up the track in the office.
Since the garage doors are reportedly on schedule for next week, Steven cleaned up the random pile of lumber stored in the garage, moving it clear of where the doors will be assembled, sweeping the floor clean, and shifting out of the way Ron’s desk, a pile of pavers and a second pile of bricks. That leaves only a second pile of dried-out 60-year-old studs that the framers cut from the garage when joining the existing two-bay structure to the new garage shed; Ron plans to recycle these.
And … between conference calls and work, Steven began assembling the specs requested by the Austin Green Build program. This homework will take a while.