Week ending 26 June 2015 part 2

Mark Rehberg from Ranserve files this week’s update.

This week:

  • Continued interior demo.
  • AC condensing units, coils and air handlers were disconnected and removed for Habitat recycling program.
  • Habitat performed the first of three pick ups.
  • East side Lumber delivered framing materials.
  • Barry with Custom Plumbing reviewed plumbing fixture selections.
  • Jonell at Ferguson’s was notified to place the order for valves/drains and we requested specification sheets for our records and for the plumber on site.
  • Received final HVAC bid from Kyle at Elite AC.  The design and specifications were completed with help from Ross Britton.  We will provide a submittal for your review and approval next week.
  • Ben Feldt confirmed that the structural design would be provided Monday June 29th.
  • Ron has lined up a framing crew for next week.
  • Wendy Shelton/wood floor consultant, visited the site and provided a favorable response to matching/sand & finish existing wood floors.  Details to be discussed next Tuesday with Ron Dahlke.

Next week:

  • Habitat pick up 7/2/15.
  • Interior framing.
  • Confirm delivery of Milgard windows from Martel Windows and Doors, due 7/8/15.