Ron Dahlke files this week’s summary:

This week:

  • Finished install of all interior doors, shelves and window trim
  • Installed kitchen countertops
  • Started paint prep on trim
  • Delivered flooring material
  • Delivered plumbing fixtures
  • Set forms for garage slab
  • Ordered backsplash tile

Next week

  • Continue on paint prep
  • Start floor install
  • Call in for layout inspection for garage slab
  • Start installing rebar in garage slab