Week ending 12 June 2015

Ron Dahlke from Ranserve reports:

This week:

  • Continued on demo.
  • Most of sheetrock is removed from downstairs area
  • Placed all items for habitat from downstairs area in garage
  • Removed and replaced trash dumpster #1.
  • Window order has been placed, tentative delivery date 7/6/2015

Next week:

  • Continue on prep upstairs
  • Remove items for habitat and place in garage from upstairs.
  • Invite plumber over to review existing conditions.
  • Finalize plumbing fixtures and have Barry with Custom Plumbing review them.
  • Continue on demo upstairs.
  • Invite engineer to job site to review framing

Critical Path for next week:

  • Plumbing fixtures ordered
  • Site visit with engineer
  • Exterior door decisions