Ron Dahlke from Ranserve reports:
This week:
- Continued on demo.
- Most of sheetrock is removed from downstairs area
- Placed all items for habitat from downstairs area in garage
- Removed and replaced trash dumpster #1.
- Window order has been placed, tentative delivery date 7/6/2015
Next week:
- Continue on prep upstairs
- Remove items for habitat and place in garage from upstairs.
- Invite plumber over to review existing conditions.
- Finalize plumbing fixtures and have Barry with Custom Plumbing review them.
- Continue on demo upstairs.
- Invite engineer to job site to review framing
Critical Path for next week:
- Plumbing fixtures ordered
- Site visit with engineer
- Exterior door decisions