The structural engineer approved the garage foundation.The City of Austin inspected and approved the grounding wire installed by Capstone to the garage foundation.The City of Austin inspected and approved the layout and formwork for the garage foundation.
Ron Dahlke schedule the concrete pour for tomorrow, Thursday, 10 December.
In addition to the concrete pour, Gilsa ripped out most of the original walk to the front door. When we extended the entry hall foward to build the stairs to code, then turned the front door sideways to face the front porch, the walk no longer connected to the new step up to the front door. Gilsa will build forms and shift the walk to better align with the new front door. The shin bone’s connected to the knee bone …Gilsa also deconstructed the stone walk from the front of the house and around the side to where the old kitchen deck has already been demo’d.