Back from NYC and “day job” earning money to pay for this remodel, tackling the to-do list:
- Manual J. Kyle from Elite advises that his math now calls for 4 tons HVAC, after reviewing numbers with Austin Energy Green Building. Kyle updated system configuration, saving the Leons approximately $500. Kyle advises he will contact AEGB with updated numbers and share copy with Steven.
HVAC observation. Emerald Hill at approximately 3200 sq ft heated will have half the HVAC "tonnage" as the Leon's existing 4200 sq ft heated -- 4 tons dual speed at Emerald Hill vs. 8 tons multispeed at Sea Eagle View. Emerald Hill is getting new insulation -- foam in the attic, blown-in in the walls, new exterior sheathing, new siding, new dual-pane insulated windows, and more, but will that suffice when Sea Eagle has foam everywhere? This math is worrisome ...
Kyle messages: "Bigger system will give you the extra capacity to cool the house more quickly if you wanted it cooler than 75 degrees when it is more than 100 outside and also will give you extra capacity if you have a lot of guests.
"The smaller system will run more often and remove humidity better and generally speaking be more efficient."
- Habitat. Mark Rehberg from Ranserve reports Habitat pickups #2 and #3 of donated items are now scheduled for 2 July and 8 July.
- Structural Engineer. Steven pinged Ben Feldt to ask for ETA on structural engineering needed for wood framing, plumbers, HVAC chases.
- Exterior siding. Brett Grinkmeyer, architect; Mark and Ron from Ranserve; and Steven will schedule a meeting at Ranserve to review options for Hardie exterior siding — what reveal, what finish, what labor budget, what materials budget.
- Front door. This is a Critical Path Item (CPI). Steven is working with Mark and Ron to identify options — wood species, paintable or stainable, glass or no glass.
- Doors. Additional exterior doors at kitchen, back door, garage, and interior doors. Mark tells Steven that Ranserve has received proposal from BMC West. Ron is reviewing. Steven asks to share.
- Door hardware/handles. Steven began contacting 2-3 weeks ago suppliers of door “jewelry” recommended by Ranserve. He’s starting to get responses.
- First draw. Steven is coordinating paperwork for first draw payment to Ranserve by SouthStar Bank SSB. It’s a process. Brett Grinkmeyer completed his architectural signoff. Kathleen Baker at Ranserve has to complete form supplied by Dawn Embry at SouthStar. Steven will sign. Larry Weisinger at SouthStar will inspect house. Ranserve will receive money.
- Plumbing fixtures. Ron, site supervisor, and Barry at Custom Plumbing are to complete review of plumbing fixtures selected by Jacquela and Steven. With that review, Kathleen from Ranserve and Steven will be able to finalize the Ferguson order.
- Flooring. Will we be able to save and refinish the existing oak floors?