Week ending 9 Oct. 2015

Ron Dahlke files this week’s construction update.

This week:

  • Primed all interior walls
  • Two coats of paint on ceiling
  • Started 1st coat of paint on walls
  • Removed all floor covering and cleaned
  • Cleaned all window frames and hardware
  • Met with glass companies
  • Met with tile setter
  • Discussed landscaping and requesting bids
  • Verified cabinets condition and location
  • Verified door hardware
  • Delivered trash trailer

Next week:

  • Continue painting walls
  • Receive interior doors and trim
  • Prime interior trim
  • Start tile install
  • Touch ups to drywall

I’ll check in with Jeff with Austin Gutter King and get his schedule options for a site visit next week.