Ron Dahlke files this week’s construction update.
This week:
- Primed all interior walls
- Two coats of paint on ceiling
- Started 1st coat of paint on walls
- Removed all floor covering and cleaned
- Cleaned all window frames and hardware
- Met with glass companies
- Met with tile setter
- Discussed landscaping and requesting bids
- Verified cabinets condition and location
- Verified door hardware
- Delivered trash trailer
Next week:
- Continue painting walls
- Receive interior doors and trim
- Prime interior trim
- Start tile install
- Touch ups to drywall
I’ll check in with Jeff with Austin Gutter King and get his schedule options for a site visit next week.