Weekly update, 12 Feb. 2016

Ron Dahlke files this week’s summary report:

This week:

  • Final repairs to cabinets underway
  • Repairs to baluster
  • Final clean starting
  • Passed final electrical inspection
  • Passed blower door test
  • Passed duct balancing test
  • Ordered replacement glass for Jadin’s bedroom
  • Installed screens — noted missing screens
  • Removed Ranserve tools, desk, and tool box from garage
  • Picked up framing items in driveway

Next week:

  • Repair plumbing corrections
  • Repair HVAC corrections
  • Complete install on hardware
  • Continue on misc repairs
  • Complete install on fire protection in garage
  • Complete low voltage install
  • Remove old tile flooring in garage
  • Remove porta potty
  • Repair and grout tile at kitchen back splash