Ron Dahlke files this week’s summary:

This week:

  • Set cabinet at entry
  • Set hardwood on stairwell
  • Finished stairwell flooring
  • Continue on finished ends of cabinets
  • Install cabinet hardware
  • Received door hardware
  • Approved engineering report on garage slab
  • Scheduled form survey for garage addition

Next week:

  • Finish covering floor
  • Set Jadin’s shower walls
  • Finish cabinet scribes
  • Continue paint on trim and doors
  • Finish sheetrock patches
  • Call in for City of Austin layout inspection for slab
  • Pour slab
  • Order framing pack for slab