Week ending 31 July 2015

Mark Rehberg, president of Ranserve, files this week’s report:

This week:

  • Continued framing, window and siding installation
  • Continued rough plumbing and rough HVAC
  • Quality control inspection of HVAC to address Steven’s concerns regarding the flex duct routing; thank you for bringing this matter to our attention.
  • Site meeting with Brett Grinkmeyer, architect

Next week:

  • Electrical rough in
  • Discuss and determine  flooring options/selections
  • Third party inspections
  • Masonry patching around windows
  • We are scheduled for the framing and rough-in inspection by the City inspector for 8/7/15

We made good progress and addressed multiple issues this week.  This project has had a good pace and we appreciate your active participation.