Mark Rehberg, president of Ranserve, files this week’s report:
This week:
- Continued framing, window and siding installation
- Continued rough plumbing and rough HVAC
- Quality control inspection of HVAC to address Steven’s concerns regarding the flex duct routing; thank you for bringing this matter to our attention.
- Site meeting with Brett Grinkmeyer, architect
Next week:
- Electrical rough in
- Discuss and determine flooring options/selections
- Third party inspections
- Masonry patching around windows
- We are scheduled for the framing and rough-in inspection by the City inspector for 8/7/15
We made good progress and addressed multiple issues this week. This project has had a good pace and we appreciate your active participation.