Ron Dahlke reports this week’s construction summary:
This week:
- Selected and grouted tile
- Primed remaining trim
- Met trim carpenters and discussed details
- Template for kitchen sink countertop
- Continued on cabinet install
- Started install on shower panels in Jadin’s bathroom
Next week:
- Continue on cabinets
- Continue on doors and trim
- Final measurements for glass doors
- I was able to order the missingĀ “h” track for the bathroom panels. They will take two weeks to come in.
- I scheduled the floor install for starting November 23.