Ron Dahlke from Ranserve files this week’s summary:
This week:
- Received final shower pan
- Set remaining plumbing for inspection
- Installed sheetrock at mud room walls
- Started insulation
- Continued on outside masonry
- Met with welder on site
- Installed cedar siding at front porch
- Ordered tile
Next week:
- Meet with Miki on the Green Build program
- Continue and finish insulation
- Call in for insulation inspection
- Receive and install remaining shower walls
- Continue exterior paint
- Shim reveals on windows
- Finish cabinet specs and start production
Steven adds:
- Steven approved kitchen cabinet plans
- Steven asked architect Brett Grinkmeyer to draw plans for potential third garage bay
- Steven continues hunt for company to install network, AV, phone and low-voltage wiring systems.