Week ending 28 Aug. 2015

Ron Dahlke from Ranserve files this week’s summary:

This week:

  • Received final shower pan
  • Set remaining plumbing for inspection
  • Installed sheetrock at mud room walls
  • Started insulation
  • Continued on outside masonry
  • Met with welder on site
  • Installed cedar siding at front porch
  • Ordered tile

Next week:

  • Meet with Miki on the Green Build program
  • Continue and finish insulation
  • Call in for insulation inspection
  • Receive and install remaining shower walls
  • Continue exterior paint
  • Shim reveals on windows
  • Finish cabinet specs and start production

Steven adds:

  • Steven approved kitchen cabinet plans
  • Steven asked architect Brett Grinkmeyer to draw plans for potential third garage bay
  • Steven continues hunt for company to install network, AV, phone and low-voltage wiring systems.