Mark Rehberg from Ranserve files this week’s update.

This week:

  • Continued demolition
  • Received approval on plumbing fixtures from S. Leon
  • On site meeting with Ben Feldt to discuss existing/planned modifications
  • On site meeting with Barry/Custom Plumbing

Next week:

  • Continue demo
  • Disconnect and remove (2) HVAC units
  • Habitat to pick up donation materials
  • Plumbing submittal finalized
  • Confirm with second opinion that existing wood floors cannot be refinished.  This is most likely the case.
  • Possibly start framing

CPI:

  • Simpson exterior door
  • Hardie siding and soffit specifications (Steve, you may want to request input from Brett)