Steven visited Emerald Hill three times today while also working from his desk computer and by phone — at 10 am after dropping off Jadin at school, at 2 pm to meet with Ron and before meeting with Renee at ProSource to select tile for the kitchen backsplash and master shower floor, and again at 4 pm after leaving ProSource and before Jadin “walked home from school.” Here are photos from the evolving day.
During the 10 am visit, Julian is hammering out a concrete tile at the entry that was damaged during construction — to be replaced.Testifying to the quality of work done by the tilesetters, it took an electric jackhammer to chip out the tile.At 2 pm, the tilesetters are gone and the tile has been replaced — and is cemented into place, along with the two tiles closest to the front door.
In between the 10 am and 2 pm trips to Emerald Hill, Steven received the first quote for the two-bay garage door from Cowart Door Systems.
At 10 am, Cezar Ernesto, left, and Ernesto Jovini are packing sandbags with roadbase for the middle island of the new garage foundation.At 2 pm, after compacting the roadbase in the center of the island, they are checking for loose fill and filling gaps.At 230, they are compacting again.At 4 pm, the middle island is finished. Cezar and Ernesto have begun to form the third island with sandbags and use the Bobcat to deliver more roadbase.At 230, Aaron arrives from the cabinet shop to test fit the horizontal storage bench that will be installed in the front entry. Ron helped Aaron pivot the bench into position while Steven stood back to use his hands to take this photo.At 4 pm, Enrique on the painting team is using wood putty to file all the nail holes in the trim installed by Shane and Peter, the carpenters. This photo was shot with Steven’s cameraphone, which opted to almost focus on the ladder in the foreground.
At 4 pm, Kathleen reported by email that Ranserve had received the wire transfer payment of Draw #5 from SouthStar Bank.
At 530, by email, Ron Dahlke reported that ATS inspected and passed the wallboard installation.