The Big Reveal begins

Above, the Big Reveal begins. The fence and gate around Emerald Hill comes down — a milestone. The fence went up at the start of demo. The kimono is open.

It may be Caucus Day in Iowa, but today begins what promises to be the final month of construction. We begin with one man down. Ron Dahlke continues his recovery from a virus. Steven arrived about 9 am attempting to keep up with carpenters, painters, garage door installers, electricians, as well as Kris, Matt and Kevin from Ranserve.

Today marks the return of Kevin to Emerald Hill after his diagnosis with Type 1 diabetes. Steven asks Kevin to speak with Jacquela about life with a pump, meter, blood sugar levels ...
Today marks the return of Kevin to Emerald Hill after his diagnosis with Type 1 diabetes. Steven asks Kevin to speak with Jacquela about life with a pump, meter, blood sugar levels …
Matt and Kris evicted the owl from the duct outside the master bedroom by banging on the ductwork. No harm was done to the owl, which flew off of its own accord. Kris sealed all three ducts with heavy construction paper to keep the owl from returning.
Matt and Kris evicted the owl from the duct outside the master bedroom by banging on the ductwork. No harm was done to the owl, which flew off of its own accord. Kris sealed all three ducts with heavy construction paper to keep the owl from returning.
DAvid Garcia's paint crew continues to finish out trim.
DAvid Garcia’s paint crew continues to finish out trim.
Peter reinstalls trim in the water closet to bath 2. The glass installers removed this trim to put in the oversized glass door and fixed panel.
Peter reinstalls trim in the water closet to bath 2. The glass installers removed this trim to put in the oversized glass door and fixed panel.
Shane gets prone on the floor of bath 2 and reaches under the vanity to install a missing baseboard. Tight fit, but committed. Power tools are too large to squeeze under the shelf.
Shane gets prone on the floor of bath 2 and reaches under the vanity to install a missing baseboard. Tight fit, but committed. Power tools are too large to squeeze under the shelf.
At about 1 pm, Peter and Shane began to test hang the front door.
At about 1 pm, Peter and Shane began to test hang the front door.

 