Week ending 5 Feb. 2016

Ron Dahlke is beating off the virus and files this week’s summary report:

This week:

  • Passed garage final electrical
  • Finish majority of interior paint
  • Finish exterior paint on garage
  • Install hot water heaters
  • Install garage doors
  • Install office track lights
  • Startup on AC unit
  • Remove temporary construction fence
  • Install exhaust fan covers

Next week:

  • Meet gutter company on site
  • Complete low voltage install on Thursday
  • Complete electrical repairs
  • Schedule electrical final
  • Schedule blower door inspection
  • Schedule duct balancing test
  • Schedule HVAC and plumbing finals
  • Demo flooring in garage
  • Repair and reinstall balusters
  • Remove items from garage
  • Remove trash from site

We will continue to punch out misc repairs.  More importantly, we will work thru the list of above inspections.  Each one needs to be passed before we can schedule the next inspection.  The goal is to schedule the final building inspection.