Week ending 3 July 2015

Ron Dahlke from Ranserve files this week’s update.

This week:

  • Received engineering specs
  • Ordered beam and header material
  • Evaluated level condition of slab and upstairs floor
  • Started framing, setting temporary walls
  • Spoke with Hvac and plumbing companies about schedule

Next week:

  • Frame 1st floor beams
  • Review interior door and trim package
  • Review exterior doors
  • Contact electrician about schedule

Hope you all have a wonderful holiday.