Ron Dahlke from Ranserve writes this week’s update:
This week:
- Framed in all windows
- Removed siding and replaced with OSB sheathing
- Removed rock from front patio
- Set new cement entry
- Third pick up of habitat items
- Plan meeting with Kyle on AC ducts for returns and supplies
- Met plumber about first floor drain lines and new subfloor beams
- Requested final bid for exterior doors and pocket doors
- Split trim and interior door orders for review
- Requested inspection by ATS Engineering for sheathing nail pattern
- Passed City of Austin layout inspection
- Ordered Tyveck house wrap
- Ordered Hardi siding
- Met with low voltage company
Next week:
- Continue on framing
- Set HVAC duct and supply lines for review
- Order interior doors
- Mock up interior door casings for review
- Start rough plumbing
- Receive windows Tuesday
- Wrap house with Tyveck
- Install windows
- Install siding
- Meet with roofer for roof condition/patches/pricing
- Continue on research for front door
Going to be a busy week.