Ron Dahlke files this week’s summary:
This week:
- Installed metal column in garage
- Complete framing on garage addition
- Complete rough electrical on garage addition
- Passed COA inspection on electrical rough and framing
- Resolved attic venting
- Continued on plumbing top out
- Picked up light fixtures
- Started install on light fixtures
- Delivered remaining trim
- Started install on balusters and hand rail
- Installed appliances
Next week:
- Site visit structural engineer Monday
- Start install on new electrical service to house
- Continue on electrical install
- Continue on plumbing install
- Start HVAC top out
- Finish countertop install
- Install glass doors
- Install front door
- Finish interior trim
- Start install on roof shingles