Week ending 1 Jan. 2016

Ron Dahlke files this week’s summary:

This week:

  • Framed walls and roof on garage addition
  • Dried in roof deck
  • Inspection and approval of sheathing install
  • Started top out on plumbing
  • Installed tile backsplash
  • Installed cabinets in bathrooms
  • Started install on hardware
  • Installed low voltage hardware

Next week:

  • Install siding on garage
  • Start prep and paint on garage
  • Do rough electrical on garage
  • Complete install on electrical in house
  • Install glass shower doors
  • Install Balusters and hand rail in stairwell
  • Complete countertop install
  • Continue on plumbing top out
  • Schedule Hvac company for top out
  • Complete change order for concrete pavers and schedule pour
  • Schedule engineer site visit for framing inspection of garage
  • Schedule COA inspections for rough electrical and framing of garage