Ron Dahlke files this week’s summary:
This week:
- Framed walls and roof on garage addition
- Dried in roof deck
- Inspection and approval of sheathing install
- Started top out on plumbing
- Installed tile backsplash
- Installed cabinets in bathrooms
- Started install on hardware
- Installed low voltage hardware
Next week:
- Install siding on garage
- Start prep and paint on garage
- Do rough electrical on garage
- Complete install on electrical in house
- Install glass shower doors
- Install Balusters and hand rail in stairwell
- Complete countertop install
- Continue on plumbing top out
- Schedule Hvac company for top out
- Complete change order for concrete pavers and schedule pour
- Schedule engineer site visit for framing inspection of garage
- Schedule COA inspections for rough electrical and framing of garage