Notes, 18 Nov. 2015

Brandon Pettit from Thomas McCarthy Inspections inspected Emerald Hill today for SouthStar Bank, as part of authorizing payment of Draw #5.

Rain cleared out. Above, the construction team is back to compact the road base for the foundation of the new garage bay.

Julian and his team of tilers installed the last two tiles at the front door -- the two tiles closest to the door.
Julian and his team of tilers installed the last two tiles at the front door — the two tiles closest to the door.
And the kitchen floor is now grouted.
And the kitchen floor is now grouted.
Shane and Peter, the carpenters, have vacated the loft they were using yesterday as the wood shop. In fact, they are done with Phase 1, expected back in December.
Shane and Peter, the carpenters, have vacated the loft they were using yesterday as the wood shop. In fact, they are done with Phase 1, expected back in December.
Share. Link. Like.

Welcome to the plumbing fixture warehouse

Ferguson today delivered the toilets, faucets and other plumbing fixtures, stacking them in the garage.

A huge step forward to completing the house.

Ron will have to shift them into the house, out of the garage, before we start taking apart the back wall of the garage. He will also schedule installation with Barry from Custom Plumbing.

 